2  History

  Major Topics on this Page
  2.1 Roman Roads
  2.2 Telford Pavements
  2.3 Macadam Pavements
  2.4 Early Bituminous Pavements
  2.5 Early Portland Cement Concrete Pavements
  2.6 Summary

In its most general sense, a road is an open, generally public way for the passage of vehicles, people, and animals.  The earliest human road builders predate recorded history by thousands of years.  With the advent of modern man, road building - the purposeful construction of general public ways - became a common sign of an advancing civilization.  Covering these roads with a hard smooth surface (pavement) helped make them durable and able to withstand traffic and the environment.  Some of the oldest paved roads still in existence were built by the Roman Empire. 

 

2.1  Roman Roads

By in large, Roman roads (see Figure 1.1) were constructed during the Republican times - the oldest road, Via Appia, dates back to 312 B.C. (Amergence Interactive, 2001).  At its height, the Roman road network consisted of over 100,000 km (62,000 miles) of roads, which is about equal to the length of the U.S. interstate system.   By law, all of the public was entitled to use Roman roads, but the maintenance of the roadway was the responsibility of the inhabitants of the district through which the road ran (which, in general, is the way the U.S. views roads today).  As the Roman Empire declined and was split in two in 395 A.D., its road network declined as well.  However, the superior quality and structure of its pavements have allowed many Roman roads to survive to this day. 

A typical Roman road structure (see Figure 1.2), as seen in the United Kingdom, consisted of four basic layers (Collins and Hart, 1936):


Figure 1.2: Roman Pavement Structure Near Radstock, England
(after Collins and Hart, 1936)

As can be seen, Roman pavements were quite thick - on the order of almost 0.9 m.  Roman road construction was not inexpensive.  Updated construction estimates of the Appian Way are about $2,000,000 per km (updated estimates following Rose, 1935 and Leger, 1875).
 

2.2  Telford Pavements

The first insight into today's modern pavements can be seen in the pavements of Thomas Telford (born 1757).  Teleford served his apprenticeship as a building mason (Smiles, 1904) and extended his masonry knowledge to bridge building.  During lean times, he carved grave-stones and other ornamental work (about 1780).  Eventually, Telford became the "Surveyor of Public Works" for the county of Salop (Smiles, 1904), thus turning his attention more to roads.  Telford attempted, where possible, to build roads on relatively flat grades (no more than a 1 in 30 slope) in order to reduce the number of horses needed to haul cargo.  Telford's pavement section was about 350 to 450 mm (14 to 18 inches) in depth and generally specified three layers. The bottom layer was comprised of large stones 100 mm (4 inches) wide and 75 to 180 mm (3 to 7 inches) in depth (Collins and Hart, 1936).  It is this specific layer which makes the Telford design unique (Baker, 1903).  On top of this were placed two layers of stones of 65 mm (2.5 inches) maximum size (about 150 to 250 mm (6 to 9 inches) total thickness) followed by a wearing course of gravel about 40 mm (1.6 inches) thick (see Figure 1.3).  It was estimated that this system would support a load corresponding to about 88 N/mm (500 lb per in. of width).

Figure 1.3: Typical Telford Road (after Collins and Hart, 1936)

 

2.3  Macadam Pavements

Macadam pavements introduced the use of angular aggregates.  John MacAdam (born 1756 and sometimes spelled "Macadam") observed that most of the paved U.K. roads in early the 1800s were composed of rounded gravel (Smiles, 1904).  He knew that angular aggregate over a well-compacted subgrade would perform substantially better.  He used a sloped subgrade surface to improve drainage (unlike Telford who used a flat subgrade surface) on which he placed angular aggregate (hand-broken with a maximum size of 75 mm (3 inches)) in two layers for a total depth of about 200 mm (8 inches) (Gillette, 1906).  On top of this, the wearing course was placed (about 50 mm thick with a maximum aggregate size of 25 mm) (Collins and Hart, 1936).  Macadam's reason for the 25 mm (1 inch) maximum aggregate size was to provide a "smooth" ride for wagon wheels.  Thus, the total depth of a typical MacAdam pavement was about 250 mm (10 inches) (refer to Figure 1.5).  MacAdam was quoted as saying "no stone larger than will enter a man's mouth should go into a road" (Gillette, 1906).  The largest permissible load for this type of design has been estimated to be 158 N/mm (900 lb per in. width).  In 1815, Macadam was appointed "surveyor-general" of the Bristol roads and was then able to use his design on numerous projects.  It proved successful enough that the term "macadamized" became a term for this type of pavement design and construction.  The term "macadam" is also used to indicate "broken stone" pavement (Baker, 1903).  By 1850, about 2,200 km (1,367 miles) of macadam type pavements were in use in the urban areas of the UK.  MacAdam realized that the layers of broken stone would eventually become "bound" together by fines generated by traffic. With the introduction of the rock crusher, large mounds of stone dust and screenings were generated (Gillette, 1906).  The increased use of these fines resulted in the more traditional dense graded base materials.  The first macadam pavement in the U.S. was constructed in Maryland in 1823.

Figure 1.5: Typical Macadam Road (after Collins and Hart, 1936)

 

2.4  The Rise of Bitumen

Up through the time of Macadam pavements, bituminous binders had not been used.  Although Roman roads used basic lime cements to hold their large stones together, roads of the late 1700s and early 1800s did not use a binder material and usually relied on aggregate interlock to provide cohesion.  Bituminous binding materials and surface layers began to show up in pavements in the early 1800s.

 

2.4.1  Tar Macadam Pavements 

A tar macadam road consists of a basic macadam road with a tar-bound surface.  It appears that the first tar macadam pavement was placed outside of Nottingham (Lincoln Road) in 1848 (Hubbard, 1910; Collins and Hart, 1936).  At that time, such pavements were considered suitable only for light traffic (i.e., not for urban streets).  Coal tar, the binder, had been available in the U.K. from about 1800 as a residue from coal-gas lighting.  Possibly this was one of the earlier efforts to recycle waste materials into a pavement! 

Soon after the Nottingham project, tar macadam projects were built in Paris (1854) and Knoxville, Tennessee (1866) (Hubbard, 1910).  In 1871 Washington, D.C. extensively used a "tar concrete" for road construction.  Sulfuric acid was used as a hardening agent and various materials such as sawdust, ashes, etc. were used in the mixture (Hubbard, 1910).  Over a seven-year period, 630,000 square meters (156 acres) were placed.  In part, due to lack of attention in specifying the tar, most of these streets failed within a few years of construction.  This resulted in tar being discredited, thereby boosting the asphalt industry (Hubbard, 1910).  However, some of these tar-bound surface courses in Washington, D.C., survived substantially longer - about 30 years.  For these mixes, the tar binder constituted about 6 percent by weight of the total mix (air voids of about 17 percent).  Further, the aggregate was crushed with about 20 percent passing the 2.00 mm (No. 10) sieve.  The wearing course was about 50 mm (2 inches) thick.  Hot tar paving products have not been used in the U.S. for many years.

As a side note, the term "Tarmac" was a proprietary product in the U.K. in the early 1900s (Hubbard, 1910).  Actually it was a plant mixed material, but was applied to the road surface "cold."  Tarmac consisted of crushed blast furnace slag coated with tar, pitch, portland cement and a resin.  Today the term "tarmac" is generic and generally refers to airport pavements (however, inappropriately).

 

2.4.2  Road Mix Surfaces

Road mixes, at the time often known as "retread", "oil processed", "surface mix" or "mixed-in-place" roads, refer to the mechanical mixing of asphalt and aggregate directly on the road bed to form a thin 25 - 100 mm (1 - 4 inch) wearing course.  Typically, the construction process was as follows (Urquhart, 1934):

  1. Place, grade and compact the aggregate road bed.

  2. Place the asphalt binder.

  3. Mix the asphalt binder and aggregate together using a tractor-pulled disk or harrow, windrow the mixed material in the center of the road, turn it, then redistributed across the road and smooth it.

  4. Compact the resultant wearing course until no movement is discernible under the roller wheels.

  5. After a few weeks to several months, spread a cover coat of fine aggregate over the surface and apply a seal coat.

These pavements were not true hot mix asphalt pavements because the asphalt was often applied as an emulsion and the mixing was done directly on the road.

 

2.4.3  Sheet Asphalt Pavements

The first pavements made from true hot mix asphalt (HMA) were called sheet asphalt pavements.  The HMA layers in this pavement were premixed and laid hot.  Baker (1903) describes this pavement system as:

Sheet asphalt became popular during the mid-1800s with the first ones being built on the Palais Royal and on the Rue St. Honore in Paris in 1858 (Abraham, 1929).  The first such pavement placed in the U.S. was in Newark, New Jersey, in 1870.  Sheet asphalt pavements are no longer built today.

 

2.4.4  Bitulithic Pavements

The final steps towards modern HMA were taken by Frederick J. Warren.  In 1901 and 1903, Warren was issued patents for an early HMA paving material and process, which he called "bitulithic".  A typical bitulithic mix contained about 6 percent "bituminous cement" and graded aggregate proportioned for low air voids.  The concept was to produce a mix which could use a more "fluid" binder than was used for sheet asphalt.  Warren received eight patents in 1903.  A review of the associated claims reveals that Warren, in effect, patented HMA, the asphalt binder, the construction of HMA surfaced streets and roads, and the overlay of "old" streets.  A rather complete set of patents.

In 1910 in Topeka, Kansas, a court ruling found that asphalt concrete mixes containing 12.5 mm (0.5 inch) maximum size aggregate did not infringe on Warren's patent (Steele and Himmelman, 1986).  Thus, HMA mixes thereafter became oriented to the smaller maximum aggregate sizes.  A typical "Topeka mix" consisted of 30 percent graded crushed rock or gravel (all passing 12.5 mm (0.5 inch) sieve, about 58 to 62 percent sand (material passing 2.00 mm (No. 10) and retained on 0.075 mm (No. 200) sieve) and 8 to 12 percent filler (material passing 0.075 mm (No. 200) sieve).  This mixture required 7.5 to 9.5 percent asphalt cement.

In 1910, Edwin C. Wallace, a retired employee of Warren Brothers, invented Warrenite-Bitulithic.  It consisted of an approximately 25 mm (1 inch) thick layer of "Finely divided mineral matter coated with bitumen rolled into a lower layer of large stone, small stone, stone dust and bitumen" (Wallace, 1910).  This was basically a sheet asphalt wearing course over hot, uncompacted bitulithic.  By adding the thin wearing course, the large aggregate of the Bitulithic mixes were not exposed directly to heavy, steel rimmed wheels that could cracked the aggregate and result in mix degradation.  By 1920, Warren's original patents had expired in the U.S. (Oglesby and Hewes, 1962) but the legacy of the Topeka mix lived on as reflected by the U.S. tendency towards finer mixes.

 

2.5  The Rise of Portland Cement Concrete (ACPA, 2001)

Although portland cement has been around since 1824 (when Joseph Aspdin, a Leeds mason took out a patent on a hydraulic cement that he coined "Portland" cement) it was not directly used in roadway pavements until the late 1800s.

 

2.5.1  The Original PCC Pavement

Portland cement concrete (PCC) was essentially invented in 1824.  In 1889, George W. Bartholomew proposed building the first PCC pavement in Bellefontaine, Ohio.  Bartholomew was convinced that his "artificial stone" (the term "concrete" had not come into use yet) was a suitable substitute for the brick and cobblestone of the day.  In order to convince the city of Bellefontaine to allow him to build his PCC pavement, Bartholomew agreed to donate all the materials and post a $5,000 bond guaranteeing the pavement's performance for five years.  In 1891, the first truly rigid pavement was mixed on site and placed in 5 ft. square forms.  In order to match the performance and appearance of the standard cobblestone pavements of the day, Bartholomew scored 100 mm (4 inch) squares into the PCC surface to give better footing for horses (a practice continued to this day, although not for horses anymore).  By 1914, portland cement had been used to pave 2,348 miles of roadway.

 

2.5.2  Innovations in Performance

By the 1930s a number of states started using de-icing salts to remove ice and snow from pavements. About the same time, surface scaling developed on many pavements in northern climates.  Research by the Portland Cement Association (PCA) and several state highway departments found that freeze and thaw cycles, accelerated by the use of de-icing salts, were causing the problem.  Further research lead to the development of air entrained PCC that was largely freeze-thaw resistant.

During the 1920's and 1930's, PCC pavement was usually constructed directly on the underlying soil. This practice was satisfactory until the 1930s when highway truck traffic increased to the point where pumping distresses began to appear on roadways carrying heavy truck traffic.  Research into this phenomenon resulted in recommendation of a non-pumping layer called a subbase (although now this layer is often referred to as the base layer) be placed under the PCC slabs. Gravel, crushed stone, and slag were commonly used as subbase material.  In the late 1940's, California began using cement-treated granular bases under concrete pavements. This practice quickly spread to other states.

 

2.5.3  Innovations in Construction

In 1946, two Iowa highway engineers, James W. Johnson and Bert Myers, conceptualized the slip form paver.  In 1949, the Iowa Highway Department constructed the first slipformed roadway, a 3 m (9 ft.) wide, 150 mm (6 inch) thick section of county road.  By placing two lanes side-by-side, a typical 6 m (18 ft.) wide county road could be built.  The paver attached to a ready mix concrete truck, which would discharge its load into the paver, then pull the paver forward.  In 1955, Quad City Construction Company developed an improved, self-propelled, track-mounted slipform paver capable of placing 8 m (24 ft.) wide slabs up to 250 mm (10 inches) thick.  In just a few years, several equipment manufacturers were marketing slipform pavers capable of placing concrete up to four lanes wide.

During the same period, central mixing replaced on-site mixing on most paving jobs.  Evaluations by several agencies showed that central-mixed concrete could be hauled from the mixer to the slipform paver in non-agitating dump trucks with no loss in workability or quality.

It was also during the late 1940's and early 1950's that paving contractors began experimenting with sawed concrete joints. Previously, joints were formed in the plastic concrete with jointing tools. These hand-formed joints often created a rough ride. After early attempts in Kansas and California, sawing was used on several projects in 1951, and soon became a standard construction method.

 

2.6  Summary

Road and pavement building has often been used as a benchmark of a civilizations advancement.  The quality and strength of many of the ancient roads has helped them survive to this very day.  The Via Appia in Rome is now over 2,300 years old and is still used today.  As the use of slave labor declined, smaller more economical roads, such as Telford and Macadam roads, began to arise.  Around the beginning of the 19th century, binding agents began to be used to assist aggregate cohesion and improve the durability of roads.  By the end beginning of the 20th century, the two principal pavement types, flexible and rigid, had taken on many of their modern qualities and were being built throughout the U.S.